The excavation site for the Kamloops Centre for the Arts with Seymour Street in the background as seen on July 31, 2026. (Image Credit: Kent Simmonds/CFJC Today File Photo)
Build Kamloops

Tower crane installation at Centre for the Arts project site to cause minor traffic impacts

Oct 11, 2026 | 6:00 AM

KAMLOOPS — A new nearly 50 metre tall crane is set to soar over downtown Kamloops after the Thanksgiving long weekend as work on the Kamloops Centre for the Arts moves into its next phase.

In a statement, the city says the tower crane that will help the facility rise from the ground will arrive next week, and there will be some temporary impacts to traffic on Seymour Street while crews work to put it in place.

On Tuesday (Oct. 13) next week, a mobile crane will arrive on site near the intersection of Seymour Street and Fourth Avenue. It will be positioned within the excavation area – the former Kamloops Daily News site – to prepare for the tower crane installation.

On Wednesday, the city says the 47.5 metre tower crane will be assembled and installed.

“This is an exciting moment for the project and a great sign of what’s to come as the Kamloops Centre for the Arts continues to take shape,” the city statement said.

Area of temporary eastbound lane closure on Seymour Street on Oct. 13 and 14.
Area of temporary eastbound lane closure on Seymour Street on Oct. 13 and 14. (Image Credit: City of Kamloops)

The temporary eastbound lane closure on Seymour Street will be in place on both Oct. 13 and 14 while the crane’s boom is lifted into position. The city notes there will be traffic control personnel and signage in place to direct traffic on the major downtown thoroughfare.

A groundbreaking for the arts centre was held in November last year, and crews are currently focused on the two-level underground parkade. The building itself is set to rise starting next year and construction is expected to wrap up in 2029.

In September, city staff said the project was on time and about $5 million under its overall $211-million budget. They also said work had advanced beyond the riskiest part of excavation, meaning costs should stay close to projections from here on out.