First of six units begin generating power at B.C.’s Site C dam
FORT ST. JOHN, B.C. — BC Hydro says the massive Site C dam project in northeastern British Columbia has started generating power.
The provincial electric utility says in a statement that the first of six generating units on the Site C dam has begun operations after completing testing and commissioning procedures.
It’s expected that the site will be in full service by fall 2025, adding about eight per cent more supply to B.C.’s electricity grid.
BC Hydro says the reservoir is now reaching more than 90 per cent full, with the water level at the dam rising by about 40 metres since late August when the filling process begun.