Permitting snag delays Heffley Creek Bridge project
KAMLOOPS — The Heffley Creek Bridge replacement project has hit a snag, but City of Kamloops officials still believe reconstruction should be complete by late spring.
The bridge was heavily damaged by spring flooding in 2017.
Utility Services Manager Greg Wightman says construction won’t get moving again on the $2.1 million project until the city receives certain permits from the provincial government.
“One of the challenges has been the archaeological permitting. We expect to have that early next week, which will allow us to ramp up construction again there,” said Wightman. “We’ll start our archaeological process next week. That should take a couple of weeks and then we should have construction back up and running again shortly after that.”